Subfloor
Borer in piles, bearers and joists
The subfloor is the part of an older Auckland house most owners never crawl into, and the part an inspector usually spends longest in. It holds the untreated timber that carries the floor, and it is often damper than anywhere else in the house, which suits several beetles. A borer inspection treats it as the first place to look.
Borer in piles, bearers and joists matters more than borer anywhere else in a house, because these members carry the floor. Common house borer in sapwood edges is usually slow damage that treatment and better ventilation can stop. Oval holes from the two-toothed longhorn, which tunnels through heartwood, and timber that is soft under a probe are more serious and can mean replacement.
A subfloor too low to move through safely is recorded as not inspected, so a report with that line has not ruled anything out.
What does a subfloor borer check look at?
It covers every timber member under the floor that can be reached: the piles, the bearers that sit on them, the joists that span between bearers, and the underside of the floorboards. Each is checked for exit holes and dust, probed where holes cluster, and read together with the ground beneath, the vents in the base of the walls and any sign of leaks from plumbing above.
-
Piles
Timber piles at ground level, where they stay wettest, and at the top, where the bearer sits.
-
Bearers
The heavy members along the pile lines. Longhorn tunnels here are the finding most likely to need a builder.
-
Joists
Sapwood edges are where the common house borer usually feeds. Ends and notches are probed.
-
Ground and air
Bare or wet soil, blocked vents, leaking pipes and the clearance under the floor.
Where the gap under the floor is too tight, or parts are boxed in, those areas are listed as not inspected. That is normal practice rather than a shortcut, but worth knowing before you rely on a report, particularly when you are buying a house with an older subfloor.
Why does a damp subfloor make borer worse?
Moisture favours every beetle found under Auckland houses. The common house borer develops fastest when relative humidity is above about 70%, the two-toothed longhorn's larval life varies with moisture and temperature, and huhu larvae keep feeding only while timber stays at about 25% moisture content or more. A damp, still subfloor with blocked vents gives all three what they need.
That is why ventilation and ground moisture belong in the plan, not as an extra. Clearing vents, fixing leaking pipes and dealing with water pooling under the house are typical recommendations. Huhu in floor framing is a sign of wet timber first and an insect problem second; see huhu in the house.
Is it borer or rot in the piles?
Not every soft pile has borer. Rot is decay caused by fungi in timber that stays wet, and it tends to show where a timber pile meets damp ground. Borer shows as exit holes and dust, with damage that follows the larval tunnels. A pile can have rot, borer or both, and the findings record which, because a borer treatment does nothing for timber that has decayed.
Searches for rotten piles usually end with a builder rather than a pest treatment. Where both are present, the moisture that caused the rot is often what let the borer thrive, so fixing the water source protects the new piles as well as the old bearers.
What does longhorn damage in bearers and joists mean?
The two-toothed longhorn, Ambeodontus tristis, is the native beetle that matters most under a house. Its larvae live for 2 to 11 years in the timber and tunnel through heartwood as well as sapwood, so a bearer that looks sound can be eaten out until only a skin of timber remains. Its oval exit holes, about 3–7 mm long, appear in autumn or early winter, and only probing shows what is inside.
Consumer NZ describes longhorn damage as usually severe, with the timber often needing replacement, while noting the beetle is found in buildings less often than the common house borer. Rimu, kahikatea and macrocarpa are its most frequent hosts. More on the beetle is in the guide to the two-toothed longhorn.
When do piles and bearers need replacing?
Replace a member when it has lost strength: it crumbles or a probe sinks in, longhorn tunnels run deep, or a pile no longer supports its bearer. Replacing a few damaged piles or a length of bearer with comparable timber in the same position is generally exempt from building consent. Complete or substantial replacement of subfloor structure is not exempt, and a full re-pile needs a consent.
The Building Act gives no fixed number of piles. A Marlborough District Council newsletter, relaying a BRANZ summary of MBIE determinations, suggests up to about 20% of piles as a rough guide, with ground conditions and each pile's structural role also weighed, and says staging the work does not get around the rule. Treat that as guidance only and check with Auckland Council. Borer damage repair and re-piling covers the consent and builder side.
What are the three main types of house piles?
NZS 3604, the standard most timber houses are built to, uses three main kinds of house piles: ordinary piles, which carry the weight of the floor straight down; braced piles, built in pairs with a diagonal brace between them; and anchor piles, set deeper to resist sideways load from wind and earthquakes. Cantilever piles are a fourth, less common bracing option. The type matters to an inspection because each one is replaced differently.
| Pile type | What it does | Minimum footing depth below cleared ground |
|---|---|---|
| Ordinary | Carries vertical load only | 200 mm |
| Braced | A pair of piles with a diagonal brace, resisting sideways load | 450 mm |
| Anchor | Resists sideways load on its own; cannot be swapped for an ordinary pile | 900 mm |
Standards New Zealand states that all timber piles are treated to H5, the hazard class for timber in contact with the ground, and that anchor piles carry an extra “A” in their brand. So yes, standard timber house piles in New Zealand are H5. Houses built before treated timber was in general use stood on untreated native piles, and those are the ones a subfloor inspection finds rotten or eaten at ground level.
How deep do house piles need to be in NZ?
It depends on the pile type and the ground. BRANZ's summary of NZS 3604 gives minimum footing depths below cleared ground of 200 mm for ordinary piles, 450 mm for braced piles and 900 mm for anchor piles, with each timber pile set in a concrete footing. Soft or expansive ground can push that deeper, and anything outside the standard needs specific design.
Cleared ground means the level after topsoil and unsuitable material are removed, not the lawn. Auckland re-piling jobs in published contractor project notes often go to 700–750 mm or more where the clay is poor. An inspection cannot see footing depth; it can only report what the pile does above ground: lean, gaps under the bearer, packing that has crushed, and timber that is soft at the ground line.
How many piles are needed for a house?
There is no single number. Pile positions follow the bearers, and NZS 3604 sets how far a bearer may span between piles and how big each footing must be from the bearer and joist spans either side. Add the braced or anchor piles the bracing calculation calls for, and a typical older Auckland bungalow ends up with dozens of piles spread across several pile lines.
For an owner, the count matters in two places. A subfloor report that lists only a handful of piles as checked, in a house that clearly has many more, has covered part of the floor. And the share of piles that need replacing decides whether repairs are exempt work or a consented re-pile, as set out under replacing piles and bearers on this page.
Concrete house piles in NZ: what still needs checking?
Concrete house piles are common in NZ, either precast piles set on a concrete footing or piles poured in place, and many villas and bungalows were re-piled in concrete decades ago. Borer cannot eat concrete, so a concrete pile itself is never a borer finding. What sits on it still can be: the bearer, the joists and the floor.
On a concrete-piled subfloor the inspection looks at the timber packers and bearers resting on each pile, the wire or bolt fixings, and the original native bearers that were often left in place when the piles were replaced. Cracked or tilted concrete piles are recorded as a structural note for a builder rather than a timber-pest finding.
Why are house piles sinking?
House piles sink when the ground or the pile gives way. The usual causes are soft or wet ground around the footing, clay that shrinks and swells with the seasons, footings that were too small or shallow, and timber piles that have rotted or been eaten at the ground line so the bearer drops onto a shrinking stump. Water pooling under the house makes every one of these worse.
The signs show above the floor first: floors that slope or bounce, doors that stick or swing open, cracked linings above door frames, and gaps under skirting boards. Under the house, a sinking pile often has a gap between pile and bearer, extra packing jammed in, or a lean. The inspection records which piles show this and whether borer or rot is part of the cause; a builder or engineer decides the fix.
How to fix piles under a house, and how new piles go in
A builder fixes failed piles by taking the load off them and replacing them. The bearer is jacked and propped, the old pile and footing are dug out, a new H5 timber or concrete pile goes into a fresh concrete footing at the required depth, and the bearer is re-fixed and the floor re-levelled. Damaged bearers are replaced at the same time. Repacking a sunken pile only lasts if the cause has been dealt with.
-
Find the cause
Rot, borer, soft ground or water. A borer finding in the bearers changes the scope of the job.
-
Support the floor
Jacks and props carry the bearer while each pile is removed.
-
New footing and pile
Hole dug to the depth the pile type needs, concrete footing poured, H5 timber or concrete pile set.
-
Re-fix and re-level
Bearer fixed to the new pile with the specified fixings, floor brought back to level.
-
Treat what stays
Sound timber that had borer is treated before it is closed up again.
Replacing a few piles like for like is generally exempt from consent; a full or substantial re-pile is consented work and, as foundations are primary structure, restricted building work for a Licensed Building Practitioner. Borer damage repair explains how that handover works.
What do house piles cost to replace?
There is no reliable published per-pile price for Auckland, and the numbers on contractor sites vary too much to quote as a range. The price of a pile job is driven by how many piles, their type and depth, access under the house, whether bearers need replacing, re-levelling, and whether a consent and engineer are needed. A full re-pile is a building project, not a maintenance job.
The practical step is to know the scope before asking for quotes. A borer inspection, at $285 + GST, records which piles and bearers have borer, rot or movement, so builders quote on the same list and you can compare like with like. Treatment of the timber that stays is a separate, smaller cost covered on the borer cost page.
Can subfloor borer be treated without replacing timber?
Yes, wherever the timber is still strong. Subfloor framing is usually bare, so a residual surface product or a borate preparation can go onto piles, bearers, joists and the underside of the floorboards. The work is timed ahead of emergence: before early summer for the common house borer, before autumn for the longhorn. Moisture fixes go in at the same time, so the treated timber dries out.
Published Auckland prices for subfloor treatment run about $450–$750 + GST, a guide only, and depend on access and the size of the house. The borer cost page breaks this down, and treating live borer explains each method.
How this part fits into a single visit, with the fee and the report it produces, is summarised under borer inspection in Auckland.
Asked before booking
How do you know if you have borer under the house?
Look at the subfloor timber with a good torch. Small round holes in joists and bearers, fine dust on top of bearers or on the ground below, and pale, clean-edged holes that look recent are the signs. Oval holes in heavy timbers suggest the two-toothed longhorn. If you cannot get under the floor, or cannot tell old holes from new, an inspection is the practical answer.
How serious is borer in piles?
It ranges from minor to structural. A few round holes in the sapwood edge of a pile usually leave the core carrying the load, and treatment with better ventilation can be enough. A pile that is soft right through, or a bearer with longhorn tunnels, has lost strength and needs a builder. The only way to tell which applies to a particular house is to probe the timber.
Can borer get into concrete piles?
No. Borer feeds on wood, so concrete piles cannot be attacked. The timber resting on them still can: bearers, joists and floorboards. Houses re-piled in concrete years ago may still have their original untreated native bearers and joists, so a subfloor on concrete piles still needs its timber checked.
Does a building report check the subfloor for borer?
A standard pre-purchase building report follows NZS 4306 and is a visual inspection, so it usually notes signs of borer the inspector can see, including in an accessible subfloor. It is not a specialist timber-pest assessment and may not say whether the borer is active. Borer in a building report explains what the usual wording can and cannot tell you.
Under the floor
- Two-toothed longhornThe native longhorn that tunnels through heartwood: oval holes, autumn emergence, damp subfloors
- Borer damage repairWhen borer damage needs a builder, which repairs are exempt from consent, re-piling and the order of work
- Treating live borerWhat treatment involves after a live borer finding: bare and finished timber, timing, moisture and follow-up
- Borer in floorboardsHouse borer and powderpost beetle in timber floors, finished versus bare boards, and when boards need replacing
Sources
- NZ Farm Forestry Association: household borer, Anobium punctatum
- NZ Farm Forestry Association: two-toothed longhorn, Ambeodontus tristis
- NZ Farm Forestry Association: huhu beetle
- Consumer NZ: borer and other pests
- MBIE: general repair, maintenance and replacement (exempt building work)
- Marlborough District Council, Building Post June 2020: pile replacement
- BRANZ Bulletin 560: pile foundations
- Standards New Zealand: house piles (NZS 3605 timber piles)
Book a subfloor borer check
The inspection is $285 + GST, credited against treatment done through the same operator. Treatment ranges sit on the cost page.